Home Water Utility Streets Projects Permits Trees About Contact Richfield Public Works Banner

6300 Block of Lyndale
(UPDATED 7/17/08)

Project Description:

The Minnesota Department of Transportation’s (Mn/DOT) Crosstown Reconstruction Project is triggering the reconstruction of Lyndale Avenue from I-35W/62 south to 64th Street.  The project involves reconstruction of Lyndale Avenue from curb to curb with replacement of adjacent sidewalk from Mn/DOT project limits north of 63rd Street traveling south to 64th Street in conjunction with placing a trunk storm sewer line in the Lyndale corridor that outlets westerly through the Lyndale Garden Center to Richfield Lake. 

Construction Staging and Detour:          STAGING PLAN       DETOUR MAP

Improvements on Lyndale Avenue are scheduled to start in August of 2008 and should be completed in less than three months. 

Lyndale Avenue will be closed to through traffic during construction.  As for the proposed detour route, north and south traffic will be redirected to Nicollet Avenue via 65th Street on the south side and 61st Street on the north side. 

Access for businesses and residents along Lyndale Avenue will be maintained during construction.

For more information please contact:

Kristin Asher
City Engineer
City of Richfield
6700 Portland Avenue
Richfield, MN 55423
(612) 861-9795
KAsher@cityofrichfield.org