Home > Public Works > Projects > Met Council Sewer Line Project along parts of 75th and 76th Streets > Metro Sewer Project Site 3
Zone 3- 75th Street, Sheridan Avenue to Xerxes Avenue
(Updated 12/17/2010)
Work Completed
-
Sanitary sewer interceptor pipe from Sheridan to Xerxes Avenue.
-
Flow Splitter Structure poured at Xerxes Avenue.
-
Storm sewer work from Sheridan to Xerxes Avenue.
-
Watermain work from Sheridan to Xerxes Avenue.
-
curb and gutter and driveway aprong replacement along 75th Street from Sheridan Avenue to Humboldt Avenue.
-
Final wear of the roadway has been placed from Sheridan Avenue to Xerxes Avenue.
-
The trail has been placed along 75th Street from Sheridan Avenue to Upton Avenue.
-
Final restoration work from Sheridan Avenue to Upton Avenue with the exception of the new fences.
Work in Progress:
Work to be Completed in the Spring of 2011:
-
Trail to be placed along 75th Street from Upton Avenue to Xerxes Avenue.
-
Repair of driveway crossings on the north side of 75th Street from Upton Avenue to Xerxes Avenue.
-
Repair/Replaement of fences along 75th Street from Sheridan Avenue to Upton Avenue.
-
Tree plantings from Sheridan Avenue to Xerxes Avenue.
-
Final restoration work from Upton Avenue to Xerxes Avenue
-
Final punch-list items along 75th Street from Sheridan Avenue to Xerxes Avenue (replacement of cracked concrete, placement of signs, etc.)
(Updated 9/24/2010)
Work Completed:
-
Sanitary sewer interceptor pipe from Sheridan to Washburn Avenue.
-
Flow Splitter Structure poured at Xerxes Avenue.
-
Storm Sewer work to Vincent Avenue.
-
Watermain work completed to Vincent Avenue.
Work in Progress:
-
Sanitary interceptor crew from Washburn to Xerxes Avenue.
-
Storm Sewer work at Vincent Avenue
-
Watermain work at Vincent/Washburn Avenues.
-
Street grading work.
(Updated 9/2/2010)
Work Completed:
Work in Progress:
-
Watermain work at Sheridan and Thomas Avenue
-
Storm sewer work at Sheridan and Thomas Avenue
-
Flow splitter structure at Xerxes Avenue 45-day cure process.
|