Metro Sewer Interceptor/Regional Trail Project Click here to view our Facebook Fan Page CONSTRUCTION SCHEDULE UPDATE (8/31/10): Construction is currently taking place in 3 areas of town. Please check back every Wednesday afternoon for the weekly updated schedule. -The first construction zone is on Diagonal Boulevard from Cedar Avenue to 72nd Street. Completed Work:
Work in Progress:
Residents should start to see the streetscape in this area coming back together in the next upcoming weeks. -The second construction zone is on 75th Street from Humboldt Avenue to Morgan Avenue. Work Completed:
Work in Progress:
-The third construction zone is on 75th Street between Sheridan and Xerxes Avenue. Work Completed:
Work in Progress:
Weekly Neighborhood Meetings: Topic: Project staff including multiple representatives from the City, Met Council, HR Green and the Contractor will hold neighborhood block meetings to discuss the schedule and anticipated impacts of the Metro Sewer Project in your area. These meetings offer an opportunity for residents to ask questions regarding the project. The Contractor will be able to discuss all impacts anticipated to each individual homeowner as well as provide a detailed construction schedule. Meeting Times: Residents are encouraged to attend one meeting before the work zone reaches their property. - Diagonal Boulevard (Diagonal Blvd and Bloomington Ave)
- 75th Street (75th St and MorganAvenue)
-75th Street (75th St and Upton Ave)
Meeting Locations: Diagonal Boulevard meetings will be held on the corner at the intersection of Diagonal Boulevard and Bloomington Avenue. 75th Street meetings will be held on the corner at the intersection of 75th Street and Morgan Avenue at 6:45 and the intersection of 75th street and Upton Avenue at 7:30. IN THE EVENT OF RAIN, NEIGHBORHOOD MEETINGS WILL BE CANCELLED! Updated 7/27/10 CONSTRUCTION WILL BEGIN 7/28/10 Construction will begin on Diagonal Boulevard at Cedar Avenue and work southwest towards 72nd Street. Tree removals and clearing/grubbing crews have moved into the area early this week. They will continue to remove trees thru next week. Construction is anticipated to begin on Humboldt Avenue at I-35W in approximately 2 weeks. (August 9, 2010) Contact Project Hotline with any questions or concerns- 612-861-0512
Updated 6/24/10 Construction is anticipated to Start July 6th, 2010!! Construction Schedule: The following locations are expected to have construction activity starting the first half of July. Diagonal Boulevard- Construction will begin on Diagonal Boulevard at Cedar Avenue and move southwest towards 72nd Street. Humboldt Avenue/75th Street- Construction is anticipated to begin on Humboldt Avenue at I-35W and work towards 75th Street. The work zone will then turn onto 75th Street and move west towards Xerxes Avenue.
updated 2/3/10 PROJECT HOTLINE 612-861-0512 The Metro Sewer Interceptor/Regional Trail Project was approved by the City Council on October 27, 2009 and is scheduled to begin in July 2010. Construction Schedule
Click the link below for a Q&A information sheet. This sheet provides answers to questions about the Metro Sewer Interceptor/Regional Trail Project. If you have any other questions that are not found in the link, please contact the project hotline at 612-861-0512. Nine Mile Creek Regional Trail updated 5/15/09 Project has been postponed until Spring of 2010 Project Summary:
Project Update 4/6/09
Project Timeline:
Documents: Contacts:
|
|
|