Home    About    Contact    Jobs    Search    Calendar   
banner
  Public Works Logo HomePublic WorksProjects > Met Council Sewer Line Project along parts of 75th and 76th Streets

Metro Sewer Interceptor/Regional Trail Project

Click here to view our Facebook Fan Page

CONSTRUCTION SCHEDULE UPDATE (8/31/10):

Construction is currently taking place in 3 areas of town. Please check back every Wednesday afternoon for the weekly updated schedule.

-The first construction zone is on Diagonal Boulevard from Cedar Avenue to 72nd Street.

Completed Work:

  • Sanitary sewer interceptor from Cedar Avenue to 72nd Street
  • New City watermain work from Cedar Avenue to 72nd Street

Work in Progress:

  • Storm sewer work from 17th Avenue to 72nd Street
  • Curb and gutter work will be starting Friday, September 3rd begging at Cedar Avenue and working towards 72nd Street.
  • Storm sewer work on Bloomington Avenue from Diagonal Boulevard to 71st Street.
  • Interceptor crew has turned west down 72nd Street working towards 11th Avenue.

Residents should start to see the streetscape in this area coming back together in the next upcoming weeks.

-The second construction zone is on 75th Street from Humboldt Avenue to Morgan Avenue.

Work Completed:

  • Sanitary sewer interceptor pipe from 76th Street bridge, north on Humbodlt Avenue where it than turned west on 75th Street through the Logan Avenue intersection.
  • Watermain work from Humbodlt Avenue to Logan Avenue

Work in Progress:

  • Storm sewer work at the intersection of 75th Street and Humboldt Avenue.
  • Sanitary sewer interceptor pipe from Logan Avenue working towards Penn Avenue.
  • Curb and gutter work will begin shortly on Humbodlt Avenue and 76th Street working north towards 75th Street.

-The third construction zone is on 75th Street between Sheridan and Xerxes Avenue.

Work Completed:

  • Sanitary sewer interceptor pipe from Sheridan Avenue through Thomas Avenue
  • Flow splitter structure poured at Xerxes Avenue.

Work in Progress:

  • Watermain work at Sheridan and Thomas Avenue
  • Storm sewer work at Sheridan and Thomas Avenue
  • Flow splitter structure at Xerxes Avenue 45-day cure process.

Weekly Neighborhood Meetings:

Topic: Project staff including multiple representatives from the City, Met Council, HR Green and the Contractor will hold neighborhood block meetings to discuss the schedule and anticipated impacts of the Metro Sewer Project in your area.

These meetings offer an opportunity for residents to ask questions regarding the project. The Contractor will be able to discuss all impacts anticipated to each individual homeowner as well as provide a detailed construction schedule.

Meeting Times: Residents are encouraged to attend one meeting before the work zone reaches their property.

   -  Diagonal Boulevard (Diagonal Blvd and Bloomington Ave)                  

  • Wednesday, September 8th at 6:00 p.m.
  • Monday, September 13th at 6:00 p.m.

     - 75th Street (75th St and MorganAvenue)

  • Wednesday, September 8th at 6:45 p.m.
  • Monday, September 13th at 6:00 p.m.

     -75th Street (75th St and Upton Ave)

  • Wednesday, September 8th at 7:30 p.m.
  • Monday, September 13th at 7:30 p.m.

Meeting Locations: Diagonal Boulevard meetings will be held on the corner at the intersection of Diagonal Boulevard and Bloomington Avenue. 75th Street meetings will be held on the corner at the intersection of 75th Street and Morgan Avenue at 6:45 and the intersection of 75th street and Upton Avenue at 7:30.

IN THE EVENT OF RAIN, NEIGHBORHOOD MEETINGS WILL BE CANCELLED!

 Updated 7/27/10      

CONSTRUCTION WILL BEGIN 7/28/10

Construction will begin on Diagonal Boulevard at Cedar Avenue and work southwest towards 72nd Street.

Tree removals and clearing/grubbing crews have moved into the area early this week. They will continue to remove trees thru next week.

Construction is anticipated to begin on Humboldt Avenue at I-35W in approximately 2 weeks. (August 9, 2010)

Contact Project Hotline with any questions or concerns- 612-861-0512

 

Updated 6/24/10

Construction is anticipated to Start July 6th, 2010!!

Construction Schedule: The following locations are expected to have construction activity starting the first half of July.

Diagonal Boulevard- Construction will begin on Diagonal Boulevard at Cedar Avenue and move southwest towards 72nd Street.

Humboldt Avenue/75th Street- Construction is anticipated to begin on Humboldt Avenue at I-35W and work towards 75th Street. The work zone will then turn onto 75th Street and move west towards Xerxes Avenue.

 

updated 2/3/10

PROJECT HOTLINE 612-861-0512

The Metro Sewer Interceptor/Regional Trail Project was approved by the City Council on October 27, 2009 and is scheduled to begin in July 2010. 

 Construction Schedule

  • Summer/Fall 2010: West end of the project (along 75th Street between Xerxes Avenue and I-35W) and east end of the project (portions of 11th Avenue, 72nd Street and Diagonal Boulevard, north of 76th Street and west of Cedar Avenue).
  • Spring to fall 2011: Central part of the project (along 76th Street from I-35W to 11th Avenue).
  • Completed in 2008: I-35W crossing and 75th Street from Sheridan Avenue to Penn Avenue.         

Click the link below for a Q&A information sheet. This sheet provides answers to questions about the Metro Sewer Interceptor/Regional Trail Project. If you have any other questions that are not found in the link, please contact the project hotline at 612-861-0512.

Q&A Information Sheet

Nine Mile Creek Regional Trail

Updated Cross Sections

updated 5/15/09

Project has been postponed until Spring of 2010

Project Summary:

Metropolitan Council Environmental Services (MCES) is preparing plans for a major project to upgrade a sanitary sewer line that serves Edina and Richfield. The project will begin at 75th Street and Xerxes Avenue and will extend east along 75th Street to I-35W. It will cross I-35W near the 76th Street bridge and extend east along 76th Street to 11th Avenue, where it will turn north. It will extend north along 11th Avenue to 72nd Street, turn east on 72nd, and extend east to Cedar Avenue on 72nd Street or on Diagonal Blvd.

A new regional sewer pipe will begin at the intersection of 75th street and Xerxes Avenue and extend east along 75th street to I-35W.  It will cross under I-35W near the 76th street bridge and extend east along 76th street to 11th Avenue, where it will turn north.  The pipe will extend north on 11th Avenue to 72nd, turn east on 72nd street, and extend east along Diagonal Boulevard to Cedar Avenue.  At that point the new pipe will connect with an existing MCES regional sewer.  (See Construction Staging map above) These improvements are aimed at meeting the long-term wastewater service needs in this area.

Project Update 4/6/09

Blaylock Plumbing Co. Flyer

The City has been notified that Blaylock Plumbing has handed out flyers to the property owners affected by the Metropolitan Council’s Sewer Project along 11th Avenue.  For clarification, the project does not require adjacent property owners to replace their existing service lines.  If property owners choose to do this there will be no benefit to the project, only to the individual property owner. 

The City does not have a contract with Blaylock Plumbing.  If an individual property owner chooses to replace their service line they can use any licensed plumber in the State of Minnesota.

If during construction the NEED to replace an individual service line does present itself (which is not anticipated) the project contractor would complete the work and the Metropolitan Council would pick up the cost of the replacement.

Please contact Liz at 612-861-9793 with any further questions.

Project Timeline:

               Click Here to View Map

New Construction Schedule
• Spring to fall 2010: West end of the project (along 75th Street between Xerxes Avenue and
I-35W) and east end of the project (portions of 11th Avenue, 72nd Street and Diagonal
Boulevard, north of 76th Street and west of Cedar Avenue).
• Spring to fall 2011: Central part of the project (along 76th Street from I-35W to 11th Avenue).
• Completed in 2008: I-35W crossing and 75th St. from Sheridan Avenue to Penn Avenue.

Documents:

Fact Sheet

Project Map

Metro Sewer Cross Sections

Power Point Presentation

Contacts:

City of Richfield Contact:
Kristin Asher, City Engineer
612-861-9795                   
KAsher@cityofrichfield.org    

Met Council Contact:
Tim O'Donnell
651-602-1269              
tim.odonnell@metc.state.mn.us       

 






Home   Webmaster   Contact   Search  
Site Powered by Revize    Login